Tutorial: Trace a finished product

Read the complete proof chain from released product definition to exact material, operation, as-built and acceptance evidence.

Learning goal

Audience

Auditors, Configuration Managers, Quality reviewers, programme users and production leads.

Goal

Answer what was designed, planned, consumed, executed, accepted and retained for one serialized product unit without changing it.

Before you begin

  • A completed product unit/build with accepted as-built evidence
  • Read access to Engineering, Manufacturing, controlled documents and traceability
  • Site and clearance scope covering the record
Use safe learning data

Observation-first is the default. Do not create retained customer, procurement, receipt, inventory, Quality, Engineering or Manufacturing records merely to complete a tutorial.

Guided journey

  1. 1
    Engineering

    Identify the unit and baseline

    Open /product-configuration
    Acting role
    Reviewer
    What to do
    Open the product unit and record its exact variant, baseline and configuration status.
    What you should observe
    The as-designed source is an immutable released snapshot.
    May change

    Nothing.

    Must remain unchanged

    Product and inventory records remain untouched.

  2. 2
    Manufacturing

    Verify the production definition

    Open /manufacturing/mbom
    Acting role
    Reviewer
    What to do
    Follow the PLM handoff to the released MBOM and then to the released manufacturing plan.
    What you should observe
    Every design line, gross/net quantity and operation allocation is exact and versioned.
    May change

    Nothing.

    Must remain unchanged

    Review cannot create material demand or stock.

  3. 3
    Manufacturing

    Review dispatch and execution

    Open /manufacturing/build-control
    Acting role
    Reviewer
    What to do
    Read ordered attempts, named operator/dispatch, resource/calibration references, WIP/labour and immutable result evidence.
    What you should observe
    Failures/retries remain visible and latest passing evidence does not erase them.
    May change

    Nothing.

    Must remain unchanged

    No operation is replayed and no resource or cost record is edited.

  4. 4
    Inventory / Assembly

    Follow material genealogy

    Open /traceability
    Acting role
    Reviewer
    What to do
    Trace the finished identity backward to exact batches, serials, containers and allocations, then forward from one component to its parent product.
    What you should observe
    The same physical and custody identities connect the ledger to as-built evidence.
    May change

    Nothing.

    Must remain unchanged

    Traceability is a query; it never moves or releases material.

  5. 5
    Manufacturing / Quality

    Confirm as-built and acceptance

    Open /manufacturing/acceptance
    Acting role
    Reviewer
    What to do
    Verify accepted results, Quality and Configuration decisions, FAT/SAT/commissioning sequence and controlled evidence hashes.
    What you should observe
    The as-built and acceptance chain points to exact immutable sources and accountable actors.
    May change

    Nothing.

    Must remain unchanged

    Review does not claim customer delivery, external acknowledgement or service release.