Flow 10 — Part requisition to fulfilment

Capture a multi-line work-centre demand, independently approve it, reserve available identities and route genuine shortages into existing governed supply workflows.

Overview

Inventory meaning

Draft, submission, approval and shortage routing are zero-stock demand events. Inventory changes only when a Materials Planner reserves an exact balance, Stores issues the resulting kit, or a separately governed transfer/receipt workflow posts custody movements.

Responsible roles

Requester / Materials Planner → different Project / Contract Manager → Materials Planner → different Stores Officer → Auditor

Process

  1. 1
    Multi-line request

    Record site, work centre, need date, priority, purpose and approved items.

    Demand only · Inventory unchanged
  2. 2
    Independent approval

    A different manager verifies the operational demand.

    Approved demand · Inventory unchanged
  3. 3
    Availability split

    Show unrestricted availability, reservations, issues and shortage per line.

    Read-only calculation
    READ ONLY
  4. 4
    Reserve available

    Planner selects exact bin, ownership and batch/serial identities.

    UNRESTRICTED → RESERVED
  5. 5
    Route shortage

    Link a verified replenishment proposal, receipt authority or transfer.

    No automatic transaction
  6. 6
    Independent issue

    A different Stores Officer scans and issues the reserved kit.

    On hand reduced by issued quantity
    REDUCED

Role handoff

Requester / Materials Planner → different Project / Contract Manager → Materials Planner → different Stores Officer → Auditor

Detailed reference chapters

Detailed steps

  1. 1

    Create one requisition containing every required approved catalogue item and quantity; confirm duplicate item lines are rejected.

  2. 2

    Submit the draft and sign in as a different Project / Contract Manager to approve or reject it.

  3. 3

    Review each line's available, reserved, issued, remaining and short quantities; confirm these are derived from current custody rather than copied into the request.

  4. 4

    As Materials Planner, select exact unrestricted balances and reserve only the available quantities into one controlled multi-line kit.

  5. 5

    For a genuine shortage, complete the normal replenishment, receipt-authority or transfer workflow, then link its verified reference and routed quantity to the affected line.

  6. 6

    Have a different Stores Officer issue the reserved kit and confirm the requisition line changes from reserved to issued without losing its downstream references.

Field-by-field practice data

Use a disposable training tenant

Request four training bolts for an assembly cell and route one shortage without creating stock. The page shows sample set A; the workbook includes independent A, B and C values.

Download all workflow samples (.xlsx)

Field names match the current application labels. Select existing approved records where shown, leave optional values blank unless they genuinely apply, and never copy fictitious TRAIN values into live work.

1
Materials Planner

Create a part requisition

Open /part-requisitions

Enter the work-centre demand and its exact line quantity, then submit it for independent approval.

Exact field nameRequirementSample value AHow to use it
Required siteSelect existingCOM-01Select the consuming site.
Requesting work centreRequiredAssembly Cell AName the demand owner.
Required dateRequired2026-10-15Use the operational need date.
PriorityRequiredNORMALEscalate only when operationally justified.
Project / programmeRequiredTRAIN-A-PROJECTRetain programme provenance.
Contract referenceRequiredTRAIN-A-CONTRACTRetain contract provenance.
Operational purposeRequiredBuild training actuator AState why the demand exists.
QuantityRequired4Enter demand in the approved item unit.
Line notesRequiredM8 batch-controlled bolts for operation 20.Add specific selection or handling constraints.

Expected result: The requisition records demand and availability; reservation or downstream sourcing remains a separate action.

End state

Every demand line remains traceable from requester and approval through exact stock issue or governed shortage action, without allowing a requisition to become autonomous procurement or inventory authority.