Flow 17 — Quality audit programme and findings

Approve a risk-based audit programme and engagement plan, execute independent fieldwork, retain immutable report and response versions, verify findings and close only after linked NCR/CAPA completion.

Overview

Inventory meaning

Quality audit records are assurance evidence only. They never create, block, move, release or adjust inventory; they never change a supplier approval or product baseline, automatically close an NCR or send an external message.

Responsible roles

Quality Audit Manager → different QA Head → different Internal Auditor → different Quality Engineer process owner → QA Head → read-only stakeholders

Process

  1. 1
    Programme

    Author risk, period, scope and criteria; QA rejects or approves immutable versions.

    Assurance schedule · Inventory unchanged
  2. 2
    Audit plan

    Assign a distinct auditor and process owner with bounded sampling and evidence.

    Independent assignment · no operational authority
  3. 3
    Fieldwork

    Assigned Internal Auditor starts and samples controlled objective evidence.

    Read/evidence activity · no stock action
  4. 4
    Report

    Submit immutable report/findings; QA accepts or requires a new version.

    Finding facts · no automatic NCR closure
  5. 5
    Response & verify

    Process owner links NCR/CAPA; QA rejects or verifies effectiveness.

    Corrective-action gate · custody unchanged
  6. 6
    Independent closure

    Close only after effective responses and closed linked NCR/CAPA records.

    Audit closed · read-only history
    READ ONLY

Role handoff

Quality Audit Manager → different QA Head → different Internal Auditor → different Quality Engineer process owner → QA Head → read-only stakeholders

Detailed reference chapters

Detailed steps

  1. 1

    As Quality Audit Manager, open Quality → Audit programmes and create programme v1 with site, period, frequency, objectives, scope, criteria, risk basis, classification and CLEAN evidence. Submit it for independent QA decision.

  2. 2

    As QA Head, reject programme v1 and confirm it remains immutable. Have the manager create/submit v2, then approve it. Under the active programme, create audit plan v1 with distinct Internal Auditor and Quality Engineer process-owner assignments.

  3. 3

    Reject plan v1 as QA, retain it, then create/submit/approve plan v2. Confirm the author, lead auditor, process owner and QA approver are four different named users.

  4. 4

    As the assigned Internal Auditor, record opening/fieldwork evidence and submit report v1. Reject it as QA, confirm it remains immutable, then submit and accept corrected report v2 with objective findings.

  5. 5

    As the assigned Quality Engineer process owner, answer each major/minor finding with root cause, correction, systemic corrective action, completion evidence, effectiveness criteria and a same-site NCR/CAPA link. QA rejects response v1 and verifies immutable response v2 as effective.

  6. 6

    Attempt closure while the linked NCR/CAPA remains open and confirm it is blocked. Complete that Flow 13 record separately, then close the audit as QA with CLEAN evidence and any follow-up date.

  7. 7

    As Supplier Quality Engineer or read-only Auditor, reconcile every actor, version, evidence link, audit/outbox fact and confirm inventory, supplier approval and product baseline state did not change.

Field-by-field practice data

Use a disposable training tenant

Draft a risk-based internal audit programme for the training site. The page shows sample set A; the workbook includes independent A, B and C values.

Download all workflow samples (.xlsx)

Field names match the current application labels. Select existing approved records where shown, leave optional values blank unless they genuinely apply, and never copy fictitious TRAIN values into live work.

1
Quality Audit Manager

Create the audit programme

Open /quality/audits

Define the period, objectives, scope and criteria, then submit to an independent approver.

Exact field nameRequirementSample value AHow to use it
SiteSelect existingCOM-01Select the audited site.
TitleRequiredTRAIN-A Q4 receiving and traceability auditUse a clear controlled title.
FrequencyRequiredANNUALSelect the approved cadence.
Period startRequired2026-10-01Start of the governed programme period.
Period endRequired2026-12-31End of the governed programme period.
ClassificationRequiredRESTRICTEDMatch the audit evidence.
ObjectivesRequiredVerify inbound authority, quarantine and batch-traceability control effectiveness.Define measurable audit objectives.
ScopeRequiredReceipt through putaway for TRAIN-A material at COM-01.Bound organisational and process coverage.
Criteria (one per line)RequiredCompany receiving procedure Batch traceability control Approved procurement clausesEnter one controlled criterion per line.
Risk basisRequiredHigh-criticality material and new supplier route.Explain why the audit is prioritised.

Expected result: The approved programme authorises later audit planning but does not alter source Quality records.

End state

One closed Quality audit retains an approved risk programme, independently approved plan, immutable rejected/replaced reports and finding responses, effective verification and closed NCR/CAPA provenance while operational authority remains in its owning modules.

Documentation version 2026.09