Flow 12 — Competitive sourcing, PO change and delivery control

Convert approved demand into a competitive commitment, govern PO amendments and quantity-balanced delivery schedules independently, retain attributable expediting history and hand supplier acceptance into inbound authority approval.

Overview

Inventory meaning

RFQ, quotation, award, PO release, amendment, delivery schedule, expediting and supplier acknowledgement create no inventory. Supplier acceptance creates a PENDING_APPROVAL receipt authority only.

Responsible roles

Buyer → different Procurement Manager → Buyer → different Procurement Manager → Buyer → different Project / Contract Manager → Auditor

Process

  1. 1
    Governed demand

    Select approved requisition or accepted vendor-replenishment demand.

    Demand only · Inventory unchanged
  2. 2
    Competitive RFQ

    Issue identical lines to at least two approved suppliers.

    Sourcing event · Inventory unchanged
  3. 3
    Supplier quotations

    Capture complete prices, compliance and promised dates.

    Commercial evidence · Inventory unchanged
  4. 4
    Independent award

    A different Procurement Manager selects one valid compliant response.

    Source decision · Inventory unchanged
  5. 5
    PO release

    Buyer submits; different manager releases exact commitment snapshot.

    Commercial commitment · Inventory unchanged
  6. 6
    Controlled change

    Buyer authors; different manager approves immutable PO and schedule versions.

    Version history · Inventory unchanged
  7. 7
    Expediting

    Record supplier risk and forecasts against the current schedule.

    Delivery signal · Inventory unchanged
  8. 8
    Supplier acceptance

    Capture acknowledgement and create pending inbound authority.

    Authority pending · Inventory unchanged
  9. 9
    Inbound approval

    Different Contract Manager approves the PO-backed ceiling.

    Approved ceiling · still no stock

Role handoff

Buyer → different Procurement Manager → Buyer → different Procurement Manager → Buyer → different Project / Contract Manager → Auditor

Detailed reference chapters

Detailed steps

  1. 1

    As Buyer, open Supply → Procurement, create an RFQ from approved unrouted demand and invite at least two active approved suppliers. Issue the draft and confirm no purchase commitment or inventory exists.

  2. 2

    Capture one complete quotation for each invited supplier with quotation identity, validity, lead time, unit price, promised date and compliance. Confirm exact decimal totals use the RFQ currency.

  3. 3

    Sign in as a different Procurement Manager. Compare both responses, confirm the Buyer cannot award, then select one current fully compliant quotation with a documented independent decision.

  4. 4

    Return as Buyer, create the PO draft from the award and verify item revision, quantity, unit price, currency and promised date are copied from the immutable sourcing evidence. Submit it.

  5. 5

    Return as Procurement Manager. Confirm the Buyer cannot release their own PO, then independently release or reject it after reviewing award, value, dates, terms and quality clauses.

  6. 6

    Before supplier acceptance, return as Buyer and create a complete PO amendment. Change a controlled value, submit it, confirm self-approval is blocked, then have a different Procurement Manager approve it. Verify the PO amendment number and automatically aligned baseline schedule both advance.

  7. 7

    As Buyer, revise the delivery schedule by splitting each PO line into one or more dated quantities. Confirm exact per-line balance and delivery-window validation, submit it, and have a different Procurement Manager approve it. Record a supplier AT RISK or recovery update against the current schedule; an out-of-window forecast must be flagged for amendment without changing the approved due date.

  8. 8

    As Buyer, record the supplier's accepted acknowledgement reference. Confirm Moduvio creates a PENDING_APPROVAL receipt authority numbered from the PO and links any part-requisition demand, but creates no ASN, receipt, stock balance or ledger row.

  9. 9

    As a different Project / Contract Manager, approve the receipt authority. As Auditor, reconcile all actors and snapshots and confirm stock remains unchanged until the normal inbound flow posts a physical receipt.

Field-by-field practice data

Use a disposable training tenant

Issue a governed-demand RFQ, capture two quotations and prepare one purchase commitment. The page shows sample set A; the workbook includes independent A, B and C values.

Download all workflow samples (.xlsx)

Field names match the current application labels. Select existing approved records where shown, leave optional values blank unless they genuinely apply, and never copy fictitious TRAIN values into live work.

1
Buyer

Create the RFQ

Open /procurement

Start from approved demand, select the published policy/route and invite at least two currently qualified suppliers.

Exact field nameRequirementSample value AHow to use it
Control modeRequiredPOLICY_GOVERNEDUse the published policy unless an approved exception route applies.
Published policy versionSelect existingTRAIN-PROCUREMENT-POLICY v1Select the active exact version.
Procurement categoryRequiredDIRECT_MATERIALChoose the applicable governed category.
CriticalityRequiredHIGHUse the demand's real criticality.
Receiving siteSelect existingCOM-01Must match governed demand and supplier scope.
Contract referenceRequiredTRAIN-A-CONTRACTRetain commercial provenance.
Project / programmeRequiredTRAIN-A-PROJECTRetain programme provenance.
CurrencyRequiredINRUse the policy-approved currency.
Quotation dueRequired2026-09-20Set a future response deadline.
Quality clausesRequiredCoC and batch traceability required; supplier scope must remain current.Use controlled supplier-facing requirements.

Expected result: RFQ and quotation activity creates no inventory; award and PO release remain independently controlled.

End state

One acknowledged purchase commitment is traceable from approved demand through competitive award, immutable PO/schedule versions and supplier expediting to an independently approved inbound ceiling, with no inventory side effect.