Flow 41 — Approved operation evidence to job and contract cost insight

Read approved Manufacturing actual-versus-baseline evidence by exact job, released product baseline, operation and immutable cost-rollup version, adding customer/contract context only when governed demand resolves uniquely.

Overview

Inventory meaning

Flow 41 is a read model over approved Flow 29/30 evidence and visible Flow 40 demand. It never allocates cost, changes a source fingerprint, creates a project/work order/demand, posts payroll/budget/GL/AP/AR/tax/payment/inventory valuation, or changes item identity, custody, current stock or stock ledger. Classified reads add audit facts only.

Responsible roles

Production Planner / Production Manager source evidence → Project / Contract Manager / Accountable Executive / Production reader read-only insight → Auditor reconciliation

Process

  1. 1
    Use approved source

    Include only the current independently APPROVED build cost-rollup and its immutable operation rows.

    Read-only source
  2. 2
    Pin exact job

    Show build, Assembly work order, external job reference, released plan version and exact product baseline.

    No job creation
  3. 3
    Resolve demand context

    Match assigned site + exact project + exact released baseline; one visible demand is unique, many remain ambiguous.

    No allocation
  4. 4
    Compare variance

    Present planned versus actual minutes/cost by currency without combining currencies or mutable Item Master values.

    No valuation
  5. 5
    Drill evidence

    Retain every operation attempt, execution, dispatch, rate-version ID and SHA-256 fingerprint.

    Sources immutable
  6. 6
    Audit isolation

    Apply tenant/site/clearance scope and record classified reads while every operational and financial witness remains unchanged.

    Audit fact only
    READ ONLY

Role handoff

Production Planner / Production Manager source evidence → Project / Contract Manager / Accountable Executive / Production reader read-only insight → Auditor reconciliation

Detailed reference chapters

Detailed steps

  1. 1

    First complete Flow 29 operation cost evidence and independently approve the Flow 30 build rollup; draft, submitted and rejected rollups do not appear in Programme insight.

  2. 2

    Open Programme → Job & contract cost insight with programme_cost:read. Filter by exact customer, project, contract, job/work-order reference or demand-association state.

  3. 3

    Verify the exact build, Assembly work order, released manufacturing-plan version, product baseline and rollup version/fingerprint before interpreting any variance.

  4. 4

    Where one governed demand line matches assigned site + project reference + exact released product baseline, read its customer, contract, order, quantity and required date. If multiple lines match, leave the build ambiguous and do not divide or assign cost.

  5. 5

    Expand operations and reconcile planned/actual minutes and cost against every retained attempt, execution, dispatch, exact rate version and fingerprint.

  6. 6

    As Auditor, prove permission denial and site/classification filtering, then compare current stock, stock ledger, custody, demand, Manufacturing sources and financial witnesses before/after the read. Only the expected classified-read audit may increase.

Field-by-field practice data

Use a disposable training tenant

Read one approved training build actual-versus-baseline by exact job and operation, prove unique then ambiguous customer-demand context, and reconcile zero operational or financial side effects. The page shows sample set A; the workbook includes independent A, B and C values.

Download all workflow samples (.xlsx)

Field names match the current application labels. Select existing approved records where shown, leave optional values blank unless they genuinely apply, and never copy fictitious TRAIN values into live work.

1
Production Planner → different Production Manager

Verify the approved Manufacturing source

Open /manufacturing/cost-rollups

Open the completed training {{case}} build rollup and verify it is the current independently APPROVED version before Programme uses it.

Exact field nameRequirementSample value AHow to use it
Exact completed-operation buildSelect existingTRAIN-A-BUILD-001Select the completed build with exact Flow 29 evidence.
Project referenceRead onlyTRAIN-A-PROJECT-001This must be the work order's stored project context.
Attributable explanationRead onlyTRAIN-A approved operational variance evidenceConfirm the source rollup explains its evidence without changing it.
Controlled rollup evidenceRead onlyTRAIN-A-COST-EVIDENCE.pdf v1Confirm the approved source carries controlled evidence.

Expected result: The exact build, job, plan, released baseline, rollup version, currency and source fingerprint are visible and immutable.

2
Project / Contract Manager

Read exact job actual versus baseline

Open /programme/cost-insights

Apply the exact work-order/project filter and reconcile the returned source identity and currency totals.

Exact field nameRequirementSample value AHow to use it
Job / work orderOptionalTRAIN-A-AWO-001Use the exact work-order, external-job or build reference.
Project referenceOptionalTRAIN-A-PROJECT-001Exact case-insensitive equality is used.
BaselineRead onlyINR 1000.000000Read from the immutable Flow 30 baseline, not Item Master.
ActualRead onlyINR 1125.000000Read the sum of every retained operation attempt.
VarianceRead onlyINR 125.000000 · 12.500000%Keep currency and threshold visible.

Expected result: The view shows only approved, assigned-site and clearance-visible evidence and creates at most the expected classified-read audit.

3
Project / Contract Manager / Accountable Executive

Confirm one unique demand context

Open /programme/cost-insights

With one visible Flow 40 demand line matching the assigned site, project and exact released baseline, inspect the association.

Exact field nameRequirementSample value AHow to use it
Unique demand contextRead only1 exact match for TRAIN-AOnly one visible matching demand may be presented as unique.
CustomerRead onlyTRAIN-A-CUSTOMERRead from the exact governed demand line.
ContractRead onlyTRAIN-A-CONTRACT-001Read from the exact governed demand line.
ProjectRead onlyTRAIN-A-PROJECT-001Retain the exact job/demand project context.

Expected result: The customer/contract context is EXACT UNIQUE MATCH and no allocation, link or source mutation is created.

4
Project / Contract Manager

Confirm ambiguity remains unallocated

Open /programme/cost-insights

Use a disposable fixture with two visible demands sharing the same site/project/exact baseline and refresh the view.

Exact field nameRequirementSample value AHow to use it
Demand associationOptionalAMBIGUOUS_MATCH for TRAIN-AUse the read-only filter to isolate unresolved context.
AmbiguousRead only1 build / 2 visible demand candidatesReview both candidates; do not treat either as assigned.
CustomerRead onlyTRAIN-A-CUSTOMER-1 / TRAIN-A-CUSTOMER-2Both possible customers remain contextual only.
ActualRead onlyINR 1125.000000 onceThe total must not duplicate for each candidate.

Expected result: The association becomes AMBIGUOUS; both candidates remain visible and the build cost appears once without split or allocation.

5
Production Manager / Planner → Auditor

Drill immutable operation lineage

Open /programme/cost-insights

Expand each operation and reconcile planned/actual minutes and cost to every execution, dispatch, exact rate version and fingerprint.

Exact field nameRequirementSample value AHow to use it
Evidence versionRead onlyTRAIN-A-MCV-001 · v1Verify the immutable rollup version and source fingerprint.
BaselineRead only10 min · INR 1000.000000Verify the exact plan operation baseline.
ActualRead only12 min · INR 1125.000000 · attempt 1Reconcile the visible execution, dispatch, rate UUID and fingerprint lineage.

Expected result: All source IDs and fingerprints agree with Flow 29/30 and no evidence row is edited.

6
Auditor

Prove permission, scope and zero side effects

Open /programme/cost-insights

Retry without programme_cost:read, with an unassigned site and below the record clearance; then compare before/after domain witnesses for an authorised read.

Exact field nameRequirementSample value AHow to use it
Customer codeRead onlyTRAIN-A-CUSTOMERA user without programme_cost:read receives 403 rather than a misleading zero.
Demand associationRead onlyNO_MATCHTenant, assigned-site and classification scope filter before demand resolution.
UnmatchedRead only0 hidden-site / above-clearance rowsConfirm hidden data is absent while the authorised classified read adds only its audit fact.
Approved build rollupsRead only1 unchanged TRAIN-A sourceManufacturing sources, demand, current_stock, stock_ledger, custody, identity, valuation, payroll, budget and accounting stay unchanged.

Expected result: Denied users receive no cost surface, hidden rows remain absent, classified reads are audited and every business/financial source count remains unchanged.

End state

One scoped, explainable operational cost view connects approved immutable build evidence to exact job/baseline context and, only when unique, governed customer/contract demand—without becoming allocation, valuation or accounting authority.

Documentation version 2026.09

Last reviewed August 2026